Q. The budget prepared to estimate the expenditure on fixed assets is known as.
(A)
Capital expenditure budget
(B)
Production overhead budget.
(C)
Administration overhead budget.
(D)
Selling and distribution overhead budget.
Correct Answer -
Option(A)