Q. Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is
  • (A) 1, 2, 4, 3, 5
  • (B) 1, 3, 2, 4, 5
  • (C) 1, 2, 3, 4, 5
  • (D) 1, 3, 4, 2, 5
πŸ’¬ Discuss
βœ… Correct Answer: (C) 1, 2, 3, 4, 5