πŸ“Š Process Planning and Cost Estimation
Q. In type of manufacturing process, material is wasted. It is in the form of chips.
  • (A) machining process
  • (B) casting process
  • (C) joining process
  • (D) forming and shaping process
πŸ’¬ Discuss
βœ… Correct Answer: (A) machining process
πŸ“Š Process Planning and Cost Estimation
Q. With the use of Jigs and fixture quality control expenses will
  • (A) reduce
  • (B) increases
  • (C) jigs and fixture are not used in any production process
  • (D) none of the mentioned
πŸ’¬ Discuss
βœ… Correct Answer: (A) reduce
πŸ“Š Process Planning and Cost Estimation
Q. What is the main cause of accidents in urban areas?
  • (A) improper planning
  • (B) extra wide roads
  • (C) additional thickness of the pavement
  • (D) traffic congestion
πŸ’¬ Discuss
βœ… Correct Answer: (A) improper planning
πŸ“Š Process Planning and Cost Estimation
Q. Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the execution of the work.
  • (A) true
  • (B) false
  • (C) ---
  • (D) ---
πŸ’¬ Discuss
βœ… Correct Answer: (A) true
πŸ“Š Process Planning and Cost Estimation
Q. is required for preliminary studies of various aspects of a work or project.
  • (A) supplementary estimate
  • (B) plinth area estimate
  • (C) revised estimate
  • (D) abstract estimate
πŸ’¬ Discuss
βœ… Correct Answer: (D) abstract estimate