Q. A can do a work in 10 days. B can do it in 15 days. They work alternately starting with A. In how many days will the work be completed?

  • (A) 5 days
  • (B) 6 days
  • (C) 7 days
  • (D) 8 days
βœ… Correct Answer: (B) 6 days
Explanation: A+B work in 2 days = 1/10 + 1/15 = 1/6 → full work in 6 days.
Explanation by: Admin
A+B work in 2 days = 1/10 + 1/15 = 1/6 → full work in 6 days.