Q. A and B can complete a work in 7 days. A alone can complete it in 21 days. B alone can complete it in?
  • (A) 10.5 days
  • (B) 14 days
  • (C) 21 days
  • (D) 28 days
βœ… Correct Answer: (A) 10.5 days

Explanation: 1/7 − 1/21 = 2/21 → time = 21/2 = 10.5 days.

Explanation by: Admin
1/7 − 1/21 = 2/21 → time = 21/2 = 10.5 days.