Q. A can complete 3/4 of a work in 15 days. How many days will he take to complete the whole work?

  • (A) 18 days
  • (B) 20 days
  • (C) 22 days
  • (D) 25 days
βœ… Correct Answer: (B) 20 days
Explanation: 3/4 work in 15 days → full work in 20 days.
Explanation by: Admin
3/4 work in 15 days → full work in 20 days.