Q. A can do a work in 6 days. B can do the same work in 12 days. How long will they take together?

  • (A) 3 days
  • (B) 4 days
  • (C) 5 days
  • (D) 6 days
βœ… Correct Answer: (B) 4 days
Explanation: 1/6 + 1/12 = 1/4.
Explanation by: Admin
1/6 + 1/12 = 1/4.