Q. If 15 workers can do a work in 20 days, how many workers are required to do it in 10 days?
β
Correct Answer: (C)
30
Explanation: Workers × days = constant → 15×20 = x×10 → x=30.
Explanation by: Admin
Workers × days = constant → 15×20 = x×10 → x=30.