Q. A can complete a work in 9 days. B can complete it in 18 days. If A works alone for 3 days, how many days will B take to finish the remaining work?
  • (A) 9 days
  • (B) 12 days
  • (C) 6 days
  • (D) 8 days
βœ… Correct Answer: (C) 6 days

Explanation: A does 1/3 work in 3 days → remaining 2/3. B's rate = 1/18 → time = 12 days.

Explanation by: Admin
A does 1/3 work in 3 days → remaining 2/3. B's rate = 1/18 → time = 12 days.