Q. A and B can complete a piece of work in 30 days, B and C in 20 days, while C and A in 15 days. If all of them work together, the time taken in completing the work will be
  • A. 13 1/3 days
  • B. 12 2/3 days
  • C. 10 days
  • D. 12 days

Correct Answer: A