Q. ……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity
β
Correct Answer: (C)
Free float
You must be Logged in to update hint/solution
Discussion
Question Analytics
483
Total Visits
3 y ago
Published
Mr. Dubey
Publisher
98%
Success Rate