Q. The best way to test the Software Project Management Plan (SPMP) is by
β
Correct Answer: (B)
inspection
Explanation by: Mr. Dubey
the best way to test the software project management plan (spmp) is by a plan inspection by the sqa team. in order to further reduce risk the duration and cost estimates should further be independently computed by people other than the original project team.