Correct Answer: (B)
inspection
Explanation: the best way to test the software project management plan (spmp) is by a plan inspection by the sqa team. in order to further reduce risk the duration and cost estimates should further be independently computed by people other than the original project team.
Explanation by: Mr. Dubey
the best way to test the software project management plan (spmp) is by a plan inspection by the sqa team. in order to further reduce risk the duration and cost estimates should further be independently computed by people other than the original project team.