Q. To be an effective aid in process improvement the baseline metrics used must be

  • (A) based on reasonable estimates from failed projects
  • (B) measured consistently across projects
  • (C) drawn from large projects only
  • (D) based only on successful projects
Share

Explanation by: Mr. Dubey
to be an effective aid in process improvement the baseline metrics used must be measured consistently across projects