Q. PERT.

  • (A) both (i) and (iii) above
  • (B) both (i) and (iv) above
  • (C) both (ii) and (iv) above
  • (D) both (ii) and (iii) above
πŸ’¬ Discuss
βœ… Correct Answer: (B) both (i) and (iv) above
Explanation: two tools for computing critical path and project completion times from activity networks are cpm &pert

Explanation by: Mr. Dubey
two tools for computing critical path and project completion times from activity networks are cpm &pert