πŸ“Š Software Testing and Quality Assurance (STQA)
Q. When should company stop the testing of a particular software?
  • (A) after system testing done
  • (B) it depends on the risks for the system being tested
  • (C) after smoke testing done
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (B) it depends on the risks for the system being tested