Q. Where does the granular molding material get loaded into?
  • (A) barrel
  • (B) hopper
  • (C) pellets
  • (D) split
πŸ’¬ Discuss
βœ… Correct Answer: (B) hopper

Explanation: in a ram or plunger type injection molding system, the granular molding material has to be first loaded into a hopper, after which, with the help of a feeding device it gets metered out inside a cylinder.


Explanation by: Mr. Dubey
in a ram or plunger type injection molding system, the granular molding material has to be first loaded into a hopper, after which, with the help of a feeding device it gets metered out inside a cylinder.