Explanation: in the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. while preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials.
Q. In the case of works which require some special types of equipment, an amount of
β
Correct Answer: (A)
1-2
Explanation by: Mr. Dubey
in the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. while preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials.
Discussion
Question Analytics
1037
Total Visits
2 y ago
Published
Mr. Dubey
Publisher
94%
Success Rate