Explanation: in the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. this area is calculated by multiplying the length and the breadth.
Q. In the plinth area method, the cost of construction is computed by the multiplication of
β
Correct Answer: (C)
plinth area and plinth area rate
Explanation by: Mr. Dubey
in the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. this area is calculated by multiplying the length and the breadth.