Q. In the plinth area method, the cost of construction is computed by the multiplication of
  • (A) plinth length and rate
  • (B) plinth breadth and rate
  • (C) plinth area and plinth area rate
  • (D) plinth volume and plinth length rate
πŸ’¬ Discuss
βœ… Correct Answer: (C) plinth area and plinth area rate

Explanation: in the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. this area is calculated by multiplying the length and the breadth.


Explanation by: Mr. Dubey
in the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. this area is calculated by multiplying the length and the breadth.