Q. In water-bound Macadam roads

  • (A) small broken stones are laid in two layers
  • (B) voids between the stones are filled by stone dust
  • (C) camber for drainage is given at the formation level itself
  • (D) all of the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) all of the above