Q. Risk monitoring process
  • (A) Extent to which a software module can be used in more than one computing program
  • (B) It involves regular monitoring of the risks identified and of new risks that develops.
  • (C) It considers each of the key risks that are identified and identifies strategies to manage the risk.
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) It involves regular monitoring of the risks identified and of new risks that develops.