Q. The total activity slack is equal to ?

  • (A) Late start time - Early start time
  • (B) Late finish time – Early finish time
  • (C) Latest allowable event occurrence time - Early finish time
  • (D) all of the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) all of the above