Q. The optimistic time represents ?
  • (A) shortest possible time in which an activity can be completed if everything goes exceptionally well
  • (B) time in which the activity is normally expected to complete under normal contingencis
  • (C) time in which an activity will take to complete in case of difficulty
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) shortest possible time in which an activity can be completed if everything goes exceptionally well