Q. In time-cost optimization of a project, crashing is done.

  • (A) On all the activities
  • (B) On all the activities lying on the critical path
  • (C) Only on activities lying on the original critical path and having flatter costslopes
  • (D) On original critical activities and those that become critical at any stage of crashing inthe order of ascending cost slope
Share