Q. In PERT analysis, the time estimates of activities and probability of their occurrence follow

  • (A) Normal distribution curve
  • (B) Poisson's distribution curve
  • (C) Beta distribution curve
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) Beta distribution curve