Q. During the construction period, price variation clause in contracts caters to

  • (A) Increase in rates of only importantmaterials
  • (B) Variation in cost in materials element, labour element and petrol-oil-lubricantelement
  • (C) Variation in total cost of the project on an ad hocbasis
  • (D) Rate of inflation
πŸ’¬ Discuss
βœ… Correct Answer: (B) Variation in cost in materials element, labour element and petrol-oil-lubricantelement