Q. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
  • (A) Longest duration
  • (B) Highest cost slope
  • (C) Least cost slope
  • (D) Shortest duration
πŸ’¬ Discuss
βœ… Correct Answer: (C) Least cost slope