Q. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

  • (A) 3.5 and 5/6
  • (B) 5 and 25/36
  • (C) 3.5 and 25/36
  • (D) 4 and 5/6
πŸ’¬ Discuss
βœ… Correct Answer: (C) 3.5 and 25/36