Q. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

  • (A) EF = ES + D
  • (B) LS = LF - D
  • (C) LF = LS + D
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above