Q. Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
  • (A) A is correct but R is not correct
  • (B) R is correct but A is not correct
  • (C) Both A and R is correct
  • (D) Both A and R is incorrect
πŸ’¬ Discuss
βœ… Correct Answer: (A) A is correct but R is not correct