Q. If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

  • (A) 4 days
  • (B) 6 days
  • (C) 10 days
  • (D) 16 days
πŸ’¬ Discuss
βœ… Correct Answer: (D) 16 days