Q. Mobilization advance up to 10% of the cost of work is given to a contractor

  • (A) On commencement of work at site for payment of loan taken by him
  • (B) For the purchase of construction materials
  • (C) For the payment of advances to labour and otherstaff
  • (D) For all activities required to start the work at site on finalization of the contract document
πŸ’¬ Discuss
βœ… Correct Answer: (D) For all activities required to start the work at site on finalization of the contract document