M Mr. Dubey • 100.64K Points Coach Q. Earliest finish of an activity is always (A) Greater than earliest event time of the following node (B) Less than earliest event time of the following node (C) Less than or equal to earliest event time of the following node (D) Greater than or equal to earliest event time of the following node Correct Answer - Option(C) Views: 584 Filed under category Construction Management Share