Q. Earliest finish of an activity is always
  • (A) Greater than earliest event time of the following node
  • (B) Less than earliest event time of the following node
  • (C) Less than or equal to earliest event time of the following node
  • (D) Greater than or equal to earliest event time of the following node
πŸ’¬ Discuss
βœ… Correct Answer: (C) Less than or equal to earliest event time of the following node