Q. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

  • (A) 50 %
  • (B) Less than 50 %
  • (C) More than 50 %
  • (D) 100 %
πŸ’¬ Discuss
βœ… Correct Answer: (C) More than 50 %