M Mr. Dubey • 100.64K Points Coach Q. A dummy activity in a network (A) Is represented by dotted line (B) Is an artificial activity (C) Does not consume time and resources (D) All of the above Correct Answer - Option(D) Views: 618 Filed under category Construction Project Management Share