πŸ“Š Chemical Engineering Plant Economics
Q. The depreciation during the year 'n', in diminishing balance method of depreciation calculation, is calculated by multiplying a fixed percentage 'N' to the
  • (A) Initial cost
  • (B) Book value at the end of (n - 1)th year
  • (C) Depreciation during the (n - 1)th year
  • (D) Difference between initial cost and salvage value
πŸ’¬ Discuss
βœ… Correct Answer: (B) Book value at the end of (n - 1)th year
πŸ“Š Chemical Engineering Plant Economics
Q. In declining balance method of depreciation calculation, the
  • (A) Value of the asset decreases linearly with time
  • (B) Annual cost of depreciation is same every year
  • (C) Annual depreciation is the fixed percentage of the property value at the beginning of the particular year
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (C) Annual depreciation is the fixed percentage of the property value at the beginning of the particular year
πŸ“Š Chemical Engineering Plant Economics
Q. The amount of simple interest during 'n' interest period is (where, i = interest rate based on the length of one interest period, p = principal)
  • (A) P.i.n.
  • (B) P(1 + i.n)
  • (C) P(1 + i)n
  • (D) P(1 - i.n)
πŸ’¬ Discuss
βœ… Correct Answer: (A) P.i.n.
πŸ“Š Chemical Engineering Plant Economics
Q. With increase in the discounted cash flow rate of return, the ratio of the total present value to the initial investment of a given project
  • (A) Decreases
  • (B) Increases
  • (C) Increases linearly
  • (D) Remains constant
πŸ’¬ Discuss
βœ… Correct Answer: (A) Decreases
πŸ“Š Chemical Engineering Plant Economics
Q. Which of the following relationship is not correct is case of a chemical process plant?
  • (A) Manufacturing cost = direct product cost + fixed charges + plant overhead costs
  • (B) General expenses = administrative expenses + distribution & marketing expenses
  • (C) Total product cost = manufacturing cost + general expenses
  • (D) Total product cost = direct production cost + plant overhead cost
πŸ’¬ Discuss
βœ… Correct Answer: (D) Total product cost = direct production cost + plant overhead cost
πŸ“Š Chemical Engineering Plant Economics
Q. Which of the following is not a mathematical method for evaluation of profitability of a chemical process plant?
  • (A) Cash reserve
  • (B) Payout period
  • (C) Rate of return on investment
  • (D) Discounted cash flow based on full life performance
πŸ’¬ Discuss
βœ… Correct Answer: (A) Cash reserve

Jump to