Principles of Management MCQs | Page - 57
Dear candidates you will find MCQ questions of Principles of Management here. Learn these questions and prepare yourself for coming examinations and interviews. You can check the right answer of any question by clicking on any option or by clicking view answer button.
β
Correct Answer: (B)
Successor
Q. An event which represents the beginning of more than one activity is known as ………..event.
β
Correct Answer: (C)
Burst
Q. If two constraints do not intersect in the positive quadrant of the graph, then
β
Correct Answer: (D)
None of the above
Q. Constraint in LP problem are called active if they
β
Correct Answer: (A)
Represent optimal solution
Q. Alternative solutions exists of an LP model when
β
Correct Answer: (B)
Objective function equation is parallel to one of the constraints
Q. While solving an LP problem, infeasibility may be removed by
β
Correct Answer: (C)
Removing a constraint
Q. ………is that sequence of activities which determines the total project time.
β
Correct Answer: (B)
Critical path
Q. Activities lying on the critical path are called………….
β
Correct Answer: (C)
Critical activities