Q. A and B can do a piece of work in 10 hours. B and C can do it in 15 hours, while A and C takes 12 hours to complete the work. B independently can complete the work in

  • (A) 12 h
  • (B) 16 h
  • (C) 20 h
  • (D) 24 h
βœ… Correct Answer: (D) 24 h

You must be Logged in to update hint/solution

πŸ“ Notes by Other Students/ Teachers


πŸ“Š Question Analytics

πŸ‘οΈ
1067
Total Visits
πŸ“½οΈ
6 y ago
Published
πŸŽ–οΈ
Praveen Singh
Publisher
πŸ“ˆ
86%
Success Rate