Q. P, Q and R can do a piece of work in 24 days, 30 days and 40 days respectively. They start the work together but R leaves days before the completion of the work. In how many days is the work done?
  • (A) 13 days
  • (B) 11 days
  • (C) 15 days
  • (D) 9 days
βœ… Correct Answer: (B) 11 days