πŸ“Š Math
Q. If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:
  • (A) 12 days
  • (B) 10 days
  • (C) 9 days
  • (D) 8 days
βœ… Correct Answer: (B) 10 days

You must be Logged in to update hint/solution

πŸ’¬ Discussion


πŸ“Š Question Analytics

πŸ‘οΈ
961
Total Visits
πŸ“½οΈ
5 y ago
Published
πŸŽ–οΈ
Ankit Singh
Publisher
πŸ“ˆ
83%
Success Rate