Q. A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?

  • (A) 24 days
  • (B) 25 days
  • (C) 27 days
  • (D) 30 days
βœ… Correct Answer: (A) 24 days