Q. A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?

  • (A) 60 days
  • (B) 30 days
  • (C) 10 days
  • (D) 20 days
  • Correct Answer - Option(B)
  • Views: 886
  • Filed under category Math

No solution found for this question.