Q. A can do a work in 6 days and B can do the same in 4 days. Both of them finish the work together and get Rs. 300. What is the share of B?
  • (A) Rs. 120
  • (B) Rs. 150
  • (C) Rs. 200
  • (D) Rs. 180
βœ… Correct Answer: (D) Rs. 180