Q. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, then find the time taken by 15 men 20 boys in doing the same type of work?

  • (A) 2 days
  • (B) 8 days
  • (C) 4 days
  • (D) 12 days
  • Correct Answer - Option(C)
  • Views: 816
  • Filed under category Math

No solution found for this question.