G Gopal Sharma • 38.32K Points Coach Math Bookmark Embed Report View In MB-Short Q. A can do ¼ of a work in 10 days. B can do ⅓ of the work in 20 days. In how many days can both A and B together do the work ? (A) 26 days (B) 30 days (C) 32 days (D) 24 days Correct Answer - Option(D) Views: 1006 Filed under category Math Share