Q. Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?

  • (A) 14
  • (B) 17
  • (C) 12
  • (D) 15
  • Correct Answer - Option(D)