M Mahesh Chandra • 6.28K Points Tutor III Math Bookmark Embed Report View In MB-Short Q. Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ? (A) 14 (B) 17 (C) 12 (D) 15 Correct Answer - Option(D) Views: 832 Filed under category Math Share