πŸ“Š Math
Q. If m men can do a work in r days, then the number of days taken by (m + n) men to do it is :
  • (A) (m+n)/mn
  • (B) (m+n)/mr
  • (C) mr/(m+n)
  • (D) r(m+n)/mn
βœ… Correct Answer: (C) mr/(m+n)