Q. X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.

  • (A) 6 days
  • (B) 8.1 days
  • (C) 5.1 days
  • (D) 7 days
βœ… Correct Answer: (C) 5.1 days

You must be Logged in to update hint/solution

πŸ“ Notes by Other Students/ Teachers


πŸ“Š Question Analytics

πŸ‘οΈ
908
Total Visits
πŸ“½οΈ
5 y ago
Published
πŸŽ–οΈ
Mahesh Chandra
Publisher
πŸ“ˆ
94%
Success Rate