Q. X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
  • (A) 6 days
  • (B) 8.1 days
  • (C) 5.1 days
  • (D) 7 days
βœ… Correct Answer: (C) 5.1 days