Q. A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in

  • (A) 7 days
  • (B) 6 days
  • (C) 4 days
  • (D) 5 days
  • Correct Answer - Option(B)