πŸ“Š Math
Q. Two men undertake a job for Rs.960. They can complete it in 16 days and 24 days respectively. They work along with a third man and take 8 days to complete it. Then the share of the third man should be
  • (A) Rs.155
  • (B) Rs.165
  • (C) Rs.150
  • (D) Rs.160
βœ… Correct Answer: (D) Rs.160

You must be Logged in to update hint/solution

πŸ’¬ Discussion


πŸ“Š Question Analytics

πŸ‘οΈ
848
Total Visits
πŸ“½οΈ
4 y ago
Published
πŸŽ–οΈ
Deepak Sahoo
Publisher
πŸ“ˆ
82%
Success Rate