Q. A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?

  • (A) 124/13 days
  • (B) 113/13 days
  • (C) 108/13 days
  • (D) 120/13 days
βœ… Correct Answer: (D) 120/13 days